Monthly Claim Workflow
Complete walkthrough for preparing, submitting, and tracking progress claims each month. Follow these steps to ensure accurate claims and smooth certification.
Monthly Timeline
Verify Survey Data is Complete
Before preparing a claim, ensure all field work for the period has been uploaded and processed.
Checklist:
- All survey videos uploaded and GPS extracted
- Road segments measured and tagged
- Assets identified and classified
- Survey linked to work package
Review BQ Quantities
Check that cumulative quantities in the BQ reflect all completed work.
What to check:
- • Segment lengths match field measurements
- • Asset counts are accurate
- • No duplicate entries
- • SOR rates are correctly linked
Create New Claim
Start a new progress claim for the current period.
Steps:
- Go to Work Package → Claims tab
- Click "New Claim"
- Set claim period (e.g., 1-31 March 2026)
- Enter a reference number if required
- Save as draft
Enter "This Claim" Quantities
For each BQ line, enter the quantity of work completed this period.
Example:
| Item | Previous | This Claim | Cumulative |
|---|---|---|---|
| Pothole repair | 150 m² | 45 m² | 195 m² |
Link Evidence
Attach survey segments and tagged assets that justify the claimed quantities.
Why this matters:
- Auditors can verify quantities against GPS-tagged evidence
- Speeds up certification review
- Creates immutable proof of work
Review Totals
Check the claim summary before submission.
Verify these amounts:
- • Gross Amount: Total before deductions
- • Retention: Percentage held back (typically 5-10%)
- • Previous Certified: Amount from prior claims
- • This Claim Net: Amount you're claiming this month
Submit Claim
When everything is verified, submit the claim for certification.
Export SOV for Client
Download the Schedule of Values (SOV) Excel file for formal submission.
Export includes:
All BQ lines, quantities, rates, amounts, and claim summary formatted for client submission.
What Happens Next?
Client reviews your claim and evidence
Claim approved — amounts are locked
Payment received — final state